We were tasked with designing, manufacturing, and installing a 14 MWp Fixed-Tilt Ground Mount system for Atlantis Foundries. Our client was Energy Partners.
We were tasked with designing, manufacturing, and installing a 14 MWp Fixed-Tilt Ground Mount system for Atlantis Foundries. Our client was Energy Partners.
We identified challenges through the site assessment, ranging from space constraints to a tight timeframe of four months. To put it in context, this was our largest project and it needed to be gotten over the line in our shortest-ever completion time.
It was important to us to involve Atlantis Foundries’ adjacent communities in the proposed Solar PV solution as they were facing an unemployment rate of 80%.
In response:
In terms of material hurdles, the raw material coil arrived two months later than expected. This meant that production of purlins would run two months late. The additional international order placed was also delayed due to Houthi forces in the Red Sea and over and above this, locally produced parts had been manufactured incorrectly.
Ramming difficulties saw two work areas (previous dumping grounds) not cleared as specified. This meant that there was concrete and steel underground, which caused approximately 10% of the posts to refuse before reaching adequate ramming depth.
In response:
As the largest project at that stage of our journey, the Fixed-Tilt Ground Mount System was successfully designed, manufactured, and installed in the shortest possible time.